The Gruyere Gold Project was discovered by Gold Road in October 2013 on the South Dorothy Hills Trend, 25 kilometres north-east of the Company’s original Yamarna Belt discovery, Central Bore.

The Gruyere Mineral Resource has since grown to 144 million tonnes grading 1.3 grams per tonne for 5.9 million ounces of contained gold, making it one of the largest undeveloped gold deposits in Australia.  Gruyere is expected to produce between 85,000 and 120,000 ounces of gold in calendar year 2019. Once steady state production is achieved the average annual production is forecast at 300,000 ounces.

Powerlines Plus were engaged by Amec Foster Wheeler Civmec Joint Venture (ACJV) in a design and construct contract for the design, supply, install, test and commission overhead power lines.

These works included more than 105kms of overhead and underground distribution power in both 11kV and 33kV, and additional electrical and communications infrastructure.

A milestone project for Powerlines Plus as we constructed this project LTI free, on time and on budget.